Transmission How Energy Storage Gets Built with Bex Sherwood (Field)
Sep 25, 2025
Bex Sherwood, Head of Development at Field and chair of Regen’s Planning Working Group, dives into the intricate world of grid-scale battery storage. She explains how projects evolve from initial planning through to operation, emphasizing the critical role of connections reform and the impact of Clean Power 2030. Bex also highlights the challenges in land acquisition, the importance of workforce diversity in STEM, and Field's innovative in-house optimization platform. Tune in for insights on aligning energy storage with community needs and the future of sustainable energy.
AI Snips
Chapters
Transcript
Episode notes
Prepare For Parallel Costs After Land Commitment
- Run land and grid processes in parallel and be ready for costs to ramp after committing to land.
- Budget for annual grid securities and escalating prep costs before ordering equipment.
Development Timelines Threaten 2030 Targets
- Typical UK development from site ID to planning can take ~4 years and cost over £1m before component orders.
- Long transformer lead times and planning timelines threaten Clean Power 2030 delivery.
Secure Gate 2 Protections Where Possible
- Use Gate 2 protections for projects that reach planning-submitted to safeguard development investment.
- Aim to secure contractual milestones (e.g., CM contracts, FID) that grant queue protections.