Insights with Don Mills and David Campbell- An Acadia Broadcasting Podcast Powering the Future: Can Saint John Become Canada’s Next Data Centre Hub?
16 snips
Feb 19, 2026 Nathan Ough, President and CEO of VoltaGrid and Saint John native, outlines a bold plan to build a massive data centre with on-site power. He discusses behind-the-meter generation, natural gas and emissions controls, supply-chain and financing scale, waterless power design, and why Saint John’s port, fiber and land make it attractive for large AI infrastructure.
AI Snips
Chapters
Transcript
Episode notes
Engineer First, Permit Later
- Don't rush permitting; re-engineer designs to address community concerns on noise and emissions.
- Nathan recommends pausing to implement quieter fans and back-compliant SCRs before formal submission.
Design Eliminates Operational Water Use
- The planned power plant will be effectively waterless for operations apart from toilets.
- Nathan emphasizes zero water consumption to counter local freshwater concerns.
Skilled Trades Drive Long-Term Jobs
- Long-term operational roles will be technicians, mechanics, electricians and welders for rotating equipment maintenance.
- Nathan expects many hires to retire at VoltaGrid under 15+ year contracts and pay at global scales.