How to Plan for 100% Efficiency
Do not start a project without getting crew count commitments for major trains mechanical electrical plumbing framing Concrete steel you're going to want to get commitments on crew sizes before you go to work Do not wait to enter in commissioning. You need to have that site work at least generally sequenced out and detailed out if you want your flow paths showing correctly number 32 Do not plan on 100% efficiency with anything right now think back When was the last project where you hit 100% of all of your activities? If you can't tell me or remember that then why in the world are you planning a project planning on 100% efficient? That's stupid like let's stop doing this number 35 Don't target