The Whole Schedule Is a Wild Yes
Every activity in a c p m schedule is a guess. We're planning a plan that can happen in most other schedules. The last planner system advocates to plan in more detail the closer you get to an activity. But it doesn't say not to plan all the way out to the end of the project. If we are skittish, then put in big brackets at the end of each activity name and tell the schedulin consultants to go to hell. I'm getting passioned about when we put together a c pum schedule, it's a wildyes.