The One Third Mile Stones

At the research laboratory, i always looked at things in stages. And so we would review the one third mile stones. We were like, air handlers have to be on. We have to be done with all change orders. Uh, owner changes, a complete 100 percent. I i know i'm repeating myself now, but, and we just said over and over and over. Then they met their dead line. The commissioning process was six weeks ahead of when it would have normally started.