Work Steps for Tact Control

When you have your tack zones identified and the standard space units within that tacked zone, you can list out each work step in the area. Then the right work package s into the right tacked wagons. Advanced taxe practitioners spend most of time here. If we do not clearly identify the work steps in each tack zone and level them with our trade partners then we will not have them cue properly in our short interval processes. And our short interval commitments may be out of flow. The more time we spend here, the better off we will be.