Don't Plan Too Far Out Ahead Too Early

In tact, you're identifying what should happen eight months ahead. You need to buy it out that way and you can't be planning things just a week or week or six weeks earlier in that amount of detail. The trade partners collaborate. They say, yeah, I need more time. I need less time. Here's the formula. We are going to contractually hold these dates... And they're focusing their supervision on getting the work done instead of trying to accomplish impossible feats.