Ep.344 - The Takt Production System - Part 8

Elevate Construction

00:00

How to Create a Stable Supply Chain

Each tacked wagon has work packages and works steps. The team had the option to use tacting or excel for this, and for the first round, they chose excel with a promise to upgrade once the system was stable. It took only a week to translate their systems from c p m into a systematic flow in its simplest form. Tacting does automatically use a programme you can simply add the sequence and it shows up in the plan. So when we have a pre-construction meeting or submittale,. we can identify an issues with it before it becomes a problem. And this is likely the best way to make work ready by seeing problems ahead of time.

Play episode from 04:28