Ep.338 - The Takt Production System - Part 2

Elevate Construction

00:00

CPM and Tact - What Is the Difference?

The sepium visual representation fools and confuses project teams into thinking there is a solid plan in the schedule hidden under the excessive detail. Sepium has been used since the 19 forties, was fully adopted as industry practice in construction by the a g c, the associated general contractors of america, in 19 65. C p m is not a tool that easily shows flow or geographical connections from one work breakdown structure to another. True c p m deceives us about how long projects take. For most users, c p m masquerades as a solid plan simply because it looks complex. Tact identifies what should happen.

Play episode from 10:21
Transcript